Central Maine Power
-
Status
Operational
Application
Non-Wires Alternatives
Size
0.5 MW | 3 MWh
-
Technology
Advanced Lead Acid
Interconnection Voltage
12.47kV
Solution
This system helped defer an $18 million transmission line upgrade that would have otherwise been needed to provide capacity and reliability to the community of Boothbay, Maine, particularly during the summer vacation season.